Lead Law Update: If I have my property tested before the testing requirement date, (for example, Phase 3 begins in October 2021), would testing completed in advance be valid and accepted?
We are regularly receiving questions regarding the new Lead Law and have created a weekly “Frequently Asked Questions” (FAQ’s) forum for you as you desire to become more informed of the Lead Law and its complexity.
This week we are featuring a common question:
Question: If I have my property tested before the testing requirement date, (for example, Phase 3 begins in October 2021), would testing completed in advance be valid and accepted?
Answer: Yes, if you complete the test in advance of the required filing date, the certificate is valid and accepted by the Public Health Department.